Brindwood Road
- Sector:Water & Utilities
- Client:eight2O/SMB, Thames Water
- Location:Chingford, North East London
- Value:£600k
Barhale were employed to upgrade the existing 225mm storm water
pipeline to a 375mm concrete pipeline in order to relieve the flooding
to property number 14, Brindwood Road and increase storage
capacity of the storm water network.
The scope of work consisted of installing 360m of new pipeline along with 8 new manholes, 2 new inspection chambers and the abandonment of the old sewer. The project was always going to be challenging due to its location on a busy residential street.
Careful planning and constant liaisons with the local council allowed it to be successfully completed. Through continuous communication with the residents of Brindwood Road, the project was made easier and in turn positive relationships were formed.