Millharbour Sewer Diversion

To facilitate the construction of several new apartment blocks,
providing 766 new homes, Barhale were engaged by the Ballymore
Group to divert an existing 1600mm sewer outside of the footprint of
the future building.

In order to provide a valuable solution to the client from the outset, Barhale
undertook extensive design feasibility studies in collaboration with their
design partner, Nicholas O’Dwyer. Through undertaking Early Contractor
Involvement at tender stage, Barhale were able to challenge the outline
design and provide an alternative solution which would be constructed
faster, cost less and reduce disruption to the surrounding area.

Maida Vale Flood Alleviation Scheme

Hundreds of homes and businesses in Maida Vale have experienced dramatic flooding from heavy summer rainfall over a number of years. Thames Water and our contractor Optimise devised a solution to reduce the flooding risk for over 350 homes and businesses. The scheme includes new sewer tunnels under local, Central London roads and two new storage tanks to be constructed under local parks. It had the potential to cause widespread nuisance and disruption.

The importance of providing timely, targeted information on the project’s progress to MPs, councillors, community leaders, businesses and residents was recognised and care was taken to keep customers informed by a variety of means. As well as traditional letters and face-to-face meetings we held weekly surgeries, a web page, a quarterly magazine for residents and a text messaging service update fortnightly or when something needed to be communicated.

Great Moor Sailing Club

As part of the legally binding Undertakings and Assurances (U&As) for HS2, Barhale were contracted by Fusion JV (Morgan Sindall, BAM Nuttall and Ferrovial Agroman) to construct a temporary road, a vehicle and boat car park, a drainage system, and a new pontoon with a concrete slipway at Great Moor Sailing club in Buckinghamshire.

The team innovated to resolve several constraints related to the project, and in the process saved money and finished construction on programme, while fully complying with stringent client specifications. The team also reduced the import of virgin materials’ by eliminating the need to remove spoil from site.

Brindwood Road

Barhale were employed to upgrade the existing 225mm storm water
pipeline to a 375mm concrete pipeline in order to relieve the flooding
to property number 14, Brindwood Road and increase storage
capacity of the storm water network.

The scope of work consisted of installing 360m of new pipeline along with 8 new manholes, 2 new inspection chambers and the abandonment of the old sewer. The project was always going to be challenging due to its location on a busy residential street.

Careful planning and constant liaisons with the local council allowed it to be successfully completed. Through continuous communication with the residents of Brindwood Road, the project was made easier and in turn positive relationships were formed.

Sussex Gardens – Trunk Water Mains Relay

Barhale were contracted By Thames Water and Crossrail to re-lay
several 200 year old Victorian Cast Iron trunk water mains in Sussex
Gardens, which is situated in close proximity to the Paddington tube
and main line stations.

Works were required to provide mitigation to any settlement, which
may have been caused as a result of the Crossrail Tunnel Boring
Machine (TBM), which passed through the area a year earlier. Barhale
were awarded this work due to their experience of working on large
diameter water mains in heavily congested trenches within central
London locations.

HS2 Euston Trial Holes

Barhale were contracted to excavate 30 trial holes across Euston area
and within the grounds of Regents Park. Additionally there were 9
window samples and 3 boreholes in the area.

Barhale successfully completed excavating trial holes in highly
sensitive locations whilst considering the impacts on local traffic,
residents and the environment. We utilised acoustic barriers across the works area to reduce our general impact and reprogrammed the works to target the most intrusive trial holes concerning traffic, to be done during the school holidays and weekends.

We also worked tirelessly as we moved through the locations to ensure the communications were carried out ahead of our works.

Rostholme Square – Sewer Rehabilitation Scheme

Rostholme Square is a small estate in Doncaster, South Yorkshire, with a history of internal and external sewer flooding. On behalf of Yorkshire Water, Barhale investigated the cause and developed a solution to resolve the problem. Intensive survey works were carried out, including flooding questionnaires sent to all the residents, giving a holistic view of the problem. The study found that the existing sewer, located in residential gardens of Holly Drive and Rostholme Square, lacked the gradient to achieve self-cleansing velocities so would therefore get blocked, causing the flooding problems. The team also found that the sewer which connected to the downstream network was unable to cope with the flows, causing some localised area flooding in the highway. The results of Barhale’s investigation works altered Yorkshire Water’s proposed solution of a pumping station to a gravity system, resulting in reduced cost and potential disruption. Our proposed solution was to relay the sewer to achieve the required gradient and divert the network connection point from its existing setting to another suitable point. This meant that the team also had to go through some allotment land.
Before

Haddenham Booster Station

Customers in the village of Haddenham, Cambridgeshire were not
receiving water pressure that met the criteria of new Ofwat (Water
Services Regulation Authority) regulations. As part of the IOS alliance
with Anglian Water, Barhale were contracted to install a new booster
station adjacent to the existing water tower in order to increase the
water pressure.

The extent of the work included installing:

• 30m of new pipework at about 225mm diameter

• A two-pump water booster kiosk

Despite the close proximity of the site to residential properties, the team took care to ensure consideration of the nearby occupants, and the fact that no complaints were received is evidence of this.

Alwoodley Rising Main Replacement

As part of Yorkshire Water’s AMP 6 programme, our team in Yorkshire
undertook a scheme to replace 930m of an existing rising main along
Wigton Lane in Leeds.

The scheme was required to replace a section of the existing cast iron
rising main which pumped waste water from Alwoodley pumping
station to the local waste water treatment works along Wigton
Lane. The existing cast iron rising main had deteriorated over the
last few years resulting in several bursts. Consequently, numerous
emergency repairs were required, causing widespread disruption to
the local residents, including road closures and diversions to the busy
surrounding road network. The installation of the new main was to
prevent bursting and resultant disruption to the area.

Market Street Flood Alleviation

Remedial measures were required in Mexborough, Yorkshire, where
a number of properties were experiencing 1 in 10 year flood events
due to hydraulically overloaded sewers. Flooding had not only
caused damage to properties, but also nearby infrastructure such as
manholes. The sewers in Market Street are a combined system receiving foul and surface water flows from an extensive upstream catchment. Historic construction works in the area associated with the canal had affected the sewers and led to issues with the network performance during periods of adverse weather. During significant storm events overloading of the sewer network could lead to overland flows affecting local properties, due to the topography. The outline solution was to construct a 700m3 storage tank to capture the excess flows and pump the flows back into the sewer network when the storm event subsided.